Minutes
of NVC Utilities Committee Meeting of December 5, 2003
Present: Chairman Crofoot,
Suellyn Fleming, by phone conference call (Judy Metcalf, Richard Brockway; John
Fancy; Beverly Crofoot, Toni Mailloux, Ed Williams. Absent: Peter Spollett
1.
The minutes of the November 7th meeting were accepted: Vote 4:0
2.
Phase I and Phase II Construction Projects Work in November was
negatively impacted by much rainy weather in the midmonth and bitter cold
weather after Thanksgiving. Phase II work by Sargent & Sargent on deep water
lines along
Shore Road
is all finished except for a handful of summer water services. Phase II work by
Lynch Construction on the
Shore Road
wastewater line and storm drainage has proceeded more slowly. With winter
closing in, the difficult decision of whether to pave now or in the spring was
raised. Bill Magruder and the Northport Selectmen preferred a paved road to
maintain this winter even though applying asphalt over frozen ground is an
unknown quantity, and the roadway will still have to be dug and trench patched
at several areas in the spring. Sargent & Sargent paved the entire road from
Sea Street
to the village limit with a 2-inch basecoat on December 4th and 5th. Lynch must
still do three pump stations on
Shore Road
to complete the I&I project. This is essential in order to get adequate
flow data for the ongoing work on Phase III Wastewater Treatment Replacement.
They also have work to do in the core village including final cleanup,
relocating a catch basin on
Sea Street
and
Bay Street
,
Sea Street
widening and paving, and a one-inch top paving coat on Broadway. These will not
be done until spring. Lynch had also agreed to do three extra projects at
relatively low cost, but it is unlikely they will be done this winter. These
include placing a French drain across the bottom of
Ruggles
Park
to intercept and redirect runoff, digging out the lower entrance to the
Community Hall to prevent freeze-up and allow access, and paving/widening
George Street
in front of the Library (a town project). When it became plain that Lynch would
not get these done soon, bids were obtained from Sargent; these came in much
higher: i.e.,
French
Drain
Ruggles
Park
$4,609, dig out Community Hall & gravel $2,233, paving by Library $2,503.
John Fancy will continue to work with Lynch to try to solve the Community Hall
problem, but the Overseers would have to approve or bid these projects.
3.
Phase III DEP and Rural Development have reviewed the Woodward
& Curran Engineering Study. There is some concern that not all avenues have
been explored and that the proposed costs in the range of $4-6 million cannot be
funded. By the standards of the 2000 census, the median income in Northport is
such that we no longer qualify for grant monies from Rural Development. DEP does
not feel they can fund more than a “few” million for this project. Richard
Brockway, in discussion with Dean Manion at the
University
of
Maine
, has arranged for a group of engineering students to take on a project to study
our problems and to see whether there are innovative technologies which might
allow us to build a more affordable system. John Fancy said that he was happy to
work with this group. Alternative means of dealing with effluent from a lagoon
system including drip irrigation, spray irrigation, and wetlands discharge will
be explored. A vote to endorse this study was unanimous 4:0. John Fancy will set
up a follow-up meeting with the Town of
Belfast
in early January to fully discuss under what circumstances and at what cost
Belfast
would be willing to let us pump into their wastewater system. We will also meet
with Rural Development, DEP, and Engineers toward the end of January.
4.
Financial Reports for the water and sewer departments were not
available from the auditor. The next pay meeting is in one week.
5.
Meeting adjourned at
3:30 p.m.
Respectfully submitted, David
D. Crofoot, Chairman